Calculation for Producing Different Molds
Time and costs for construction of all arches
with Multiarc:
Time and costs for construction
of wooden basket molds:
Time and costs for construction
of wooden round molds:
Time and costs for construction
of wooden round molds for light walls:
Multiarc
Mold
|
Basket Arch
160/50/30 Round Arch 120/60/30
Round Arch (light walls) 120/60/12 |
|
|
|
All
arches spanning from 70 to 170 cm are possible |
|
Time/Amount |
Net Price |
Total |
|
Preparation in workshop or on site |
|
|
in Euro |
in Euro |
|
Adjustment of all arches max 5 minutes |
Wages |
0,08 |
36,00 |
2,88 |
|
Material: |
|
|
|
|
|
Molding system app. 25 uses in 5 years |
|
25,00 |
1.190,00 |
47,60 |
|
Or app. 15 arches per year |
|
- |
- |
- |
|
Assembling on site: |
|
|
|
|
|
1 person 5 min |
Wages |
0,05 |
36,00 |
1,80 |
|
Poles and petty materials |
|
- |
- |
- |
|
Removal and cleaning: |
|
|
|
|
|
1 person 3 min |
Wages |
0,05 |
36,00 |
1,80 |
|
Dump/transport |
|
- |
- |
- |
|
|
|
|
|
|
|
Net costs for basket arch 160/50/30 |
|
|
Euro
|
54,08 |
back to beginning
Time
and costs for construction of wooden basket molds:
|
Wooden Basket Mold 160/50/30 cm |
|
|
|
|
|
Time/Amount |
Net Price |
Total |
|
Preparation in workshop or on site |
|
|
|
|
Drawing, cutting out and assembling |
Wages |
2,75 |
36,00 |
99,00 |
|
Material: |
|
|
|
|
|
Plywood, rough mold, nails |
|
1,00 |
14,00 |
14,00 |
|
Machines (time) |
|
0,50 |
17,00 |
8,50 |
|
Assembling on site: |
|
|
|
|
|
2 people 12 min |
Wages |
0,40 |
36,00 |
14,40 |
|
Poles and petty materials |
|
1,00 |
1,40 |
1,40 |
|
Removal and disposal: |
|
|
|
|
|
1 person 15 min |
Wages |
0,25 |
36,00 |
9,00 |
|
Dump/transport |
|
1,00 |
14,00 |
14,00 |
|
|
|
|
|
|
|
Net costs for basket arch 160/50/30 |
|
Euro |
160,30 |
back to beginning
Time
and costs for construction of wooden round molds:
|
Wooden round arch 120/60/30 cm |
|
|
|
|
|
Time/Amount |
Net Price |
Total |
|
Preparation in workshop or on site |
|
|
|
|
Drawing, cutting out and assembling |
Wages |
1,50 |
36,00 |
54,00 |
|
Material: |
|
|
|
|
|
Plywood, rough mold, nails |
|
1,00 |
15,86 |
15,86 |
|
Machines (time) |
|
0,25 |
17,00 |
4,25 |
|
Assembling on site: |
|
|
|
|
|
2 people 10 min |
Wages |
0,34 |
36,00 |
12,24 |
|
Poles and petty materials |
|
1,00 |
1,40 |
1,40 |
|
Removal and disposal: |
|
|
|
|
|
1 person 15 min |
Wages |
0,25 |
36,00 |
9,00 |
|
Dump/transport |
|
1,00 |
14,00 |
14,00 |
|
|
|
|
|
|
|
Wooden round arch 120/60/30 cm |
Euro |
110,75 |
back to beginning
Time
and costs for construction of wooden round molds for light walls:
|
Wooden round arch 120/60/12 cm |
for light walls |
|
|
|
|
|
Time/Amount |
Net Price |
Total |
|
Preparation in workshop or on site |
|
|
|
|
Drawing, cutting out and assembling |
Wages |
1,00 |
36,00 |
36,00 |
|
Material: |
|
|
|
|
|
Plywood, rough mold, nails |
|
1,00 |
7,10 |
7,10 |
|
Machines (time) |
|
0,25 |
1700 |
4,25 |
|
Assembling on site: |
|
|
|
|
|
1 person 10 min |
Wages |
0,20 |
36,00 |
7,20 |
|
Poles and petty materials |
|
1,00 |
1,14 |
1,14 |
|
Removal and disposal: |
|
|
|
|
|
1 person 10 min |
Wages |
0,10 |
36,00 |
3,60 |
|
Dump/transport |
|
1,00 |
6,20 |
6,20 |
|
|
|
|
|
|
|
Net costs for round arches 120/60/12 |
|
Euro |
65,49 |